PRR Project
Unidade de Saúde de Mira Sintra
Project sheet
Name
Unidade de Saúde de Mira SintraTotal project amount
1,53 million €Amount paid
0 €Non-refundable funding
1,53 million €Loan funding
0 €Start date
02.01.2024Expected end date
30.06.2026Dimension
ResilienceComponent
National Health ServiceInvestment
Primary Health Care with greater responsiveness ratesOperation code
17/C01-i01/2023.P7655Summary
O projeto de construção das instalações da nova USF de Mira Sintra integra obras de conservação e beneficiação que visam garantir um bom funcionamento dos serviços prestados, a segurança e o conforto de utentes e profissionais e a melhoria da eficiência energética. A construção será apoiada no sistema tradicional de betão armado, melhorados com as exigências térmicas e acústicas. As paredes exteriores serão construídas por tijolo térmico e reboco térmico exterior, que garante também o revestimento da estrutura, acabada com barramento e pintura em parede ventilada.A cobertura será em tela asfáltica com proteção mecânica (lajetas) com isolamento térmico. Todos os remates e caleiras serão em peças continuas metálicas para garantia de estanquicidade.As paredes interiores serão compostas por painéis de gesso cartonado de dupla face, revestidas a painéis de madeira laminados coloridos.Os pavimentos serão revestidos de peças cerâmicas de grandes formatos para zonas de circulação, e vinílico de rolo com tratamento de superfície para espaços hospitalares em gabinetes.A caixilharia será de perfis de alumínio termolacado de cor cinza escuro com vidro fosco de caraterísticas térmicas e acústicas.Os espaços exteriores serão revestidos de material permeável para boa absorção das chuvas.O objetivo da escolha de materiais é com base no conforto, baixa manutenção e excelente durabilidade.O investimento total da construção é de 1.925.000€ (sem IVA incluído)
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
1,53 million €
Total amount of the project
Where was the money spent
By county
1 county financed .
-
Sintra 1,53 million € ,