Information portal on various topics of management of public resources of the Portuguese State

PRR Project

Unidade de Saúde de Caria - Obras de adaptação para funcionamento da nova extensão de saúde (Eficiência Energetica

Project sheet

Name

Unidade de Saúde de Caria - Obras de adaptação para funcionamento da nova extensão de saúde (Eficiência Energetica

Total project amount

123 thousand €

Amount paid

0 €

Non-refundable funding

123 thousand €

Loan funding

0 €

Start date

02.01.2024

Expected end date

31.12.2024

Dimension

Resilience

Component

National Health Service

Investment

Primary Health Care with greater responsiveness rates

Operation code

14/C01-i01/2023.P4669

Summary

dentificada a principal debilidade do edifício, as frágeis condições térmicas e de climatização, esta candidatura pretende dotar o Centro de Saúde de Belmonte das condições adequadas de isolamento térmico / climatização, que permita um incremento significativo nas condições de conforto e segurança disponibilizadas aos utentes e profissionais de saúde que nele laboram. Estas intervenções irão desencadear um conjunto de medidas que permitirão uma redução significativa da “fatura energética” do edifício, potenciando a eficiência energética do espaço, nomeadamente: - Aplicação de isolamento pelo exterior, bem como todos os trabalhos inerentes à sua intervenção; - Instalação de sistema solar fotovoltaico ligado à rede de baixa tensão; - Substituição da caixilharia existente; - Substituição da iluminação (LED); - Remodelação de Instalação de Climatização - Reabilitação e acabamento de trabalhos após a intervenções;Pretendeu-se adotar soluções construtivas e tecnológicas pouco dispendiosas e de rápida implementação.No que diz respeito ao comportamento face ao fogo, a classe das placas de gesso cartonado a aplicar (sistema de isolamento térmico pelo exterior) deverão ser, no mínimo, M1 – Não inflamável.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

2,5
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

123 thousand €

Total amount of the project

Where was the money spent

By county

1 county financed .

  • Belmonte 123 thousand € ,
Source EMRP
10.02.2026
All themes
Transparency without leading