Project sheet

Name

Obras de reformulação dos espaços de apoio de Radiologia e Radiologia de Intervenção

Total project amount

694,97 thousand €

Amount paid

0 €

Non-refundable funding

694,97 thousand €

Loan funding

0 €

Start date

29.08.2025

Expected end date

31.12.2025

Dimension

Resilience

Component

National Health Service

Investment

Construction of the East Lisbon Hospital and equipment for hospitals in Lisbon and the Tagus Valley

Operation code

05/C01-i04/2025.P24169

Summary

O projeto consiste na remodelação dos espaços de apoio dos serviços de Radiologia e Radiologia de Intervenção no Piso 3 do edifício de cirurgia (edifício A), criando as necessárias condições para a operacionalização dos novos equipamentos de imagem – o Angio-TAC e TAC de Biópsias – e para o esperado aumento do número de intervenções, adequando as instalações aos standards atualmente exigidos em termos de legislação hospitalar. Os espaços intervencionados apresentavam condições muito deficitárias, em termos de capacidade de acolhimento de doentes e ao nível infraestrutural - ausência de casas de banho para os doentes, ausência de áreas de observação capazes, ausência de vestiários, ausência de sala de sujos-, pelo que a substituição de um angiógrafo por equipamento composto de dois elementos – a Angiografia e a TAC – e a instalação de novo equipamento TAC a ser totalmente dedicado a procedimentos de intervenção tornou imperativa a intervenção infraestrutural. O investimento tem como objetivos específicos:1. Adequar as instalações à transformação operada pela instalação de equipamentos de imagem mais diferenciados, garantindo as condições físicas exigidas no percurso do doente de acordo com as normas em vigor. 2. Proporcionar mais conforto ao doente. 3. Melhorar as condições de segurança para doentes e profissionais através da otimização da circulação e dos espaços.A intervenção infraestrutural, além de adequar as instalações aos standards atualmente exigidos e normas em vigor, permite aumentar a capacidade de resposta dos serviços perante os desafios colocados pelo aumento de doentes com cancro e cada vez mais complexos devido à idade mais avançada e à existência de co-morbilidades.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

2,5
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

694,97 thousand €

Total amount of the project

Where was the money spent

By county

1 county financed .

  • Porto 694,97 thousand € ,
Source EMRP
10.02.2026
All themes
Transparency without leading