Name

Telhado do Edifício do INEM - Coberturas do INEM e VMER e substituição de vãos

Total project amount

46,71 thousand €

Amount paid

11,68 thousand €

Non-refundable funding

46,71 thousand €

Loan funding

0 €

Start date

15.09.2025

Expected end date

15.11.2025

Dimension

Resilience

Component

National Health Service

Investment

Construction of the East Lisbon Hospital and equipment for hospitals in Lisbon and the Tagus Valley

Operation code

05/C01-i04/2025.P18058

Summary

A presente operação visa a reabilitação e melhoria da eficiência energética das casas do INEM e das equipas VMER, através da substituição integral de vãos envidraçados (janelas e portas) e da cobertura dos edifícios, garantindo condições adequadas de conforto, segurança e desempenho térmico. Estas infraestruturas, integradas na rede operacional do Serviço Nacional de Saúde, têm um papel essencial na resposta a emergências médicas pré-hospitalares, funcionando como base para as equipas que asseguram a prestação de cuidados urgentes.A intervenção proposta insere-se no investimento RE-C01-i04 do PRR – Modernização das infraestruturas e equipamentos das instituições do SNS, previsto na Componente C01 – Saúde, e contribui diretamente para os objetivos estratégicos do Plano de Recuperação e Resiliência, nomeadamente o reforço da resiliência do sistema de saúde, a redução das assimetrias territoriais, a promoção da eficiência energética no setor público e o cumprimento do princípio “Do No Significant Harm” (DNSH).A substituição dos elementos construtivos degradados por soluções com elevado desempenho térmico e baixo impacto ambiental permitirá reduzir significativamente as necessidades energéticas das instalações, melhorar as condições de trabalho dos profissionais de saúde e reforçar a prontidão da resposta médica de emergência. Adicionalmente, a operação valoriza o edificado público existente, promove a coesão social e territorial, e reforça a confiança das populações nos serviços de saúde de proximidade, contribuindo para um SNS mais moderno, sustentável e inclusivo.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

2,5
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

46,71 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 25 %,

Where was the money spent

By county

1 county financed .

  • Guimarães 46,71 thousand € ,
Source EMRP
10.02.2026