Name
Remodelação da UCITotal project amount
1,84 million €Amount paid
461,25 thousand €Non-refundable funding
1,84 million €Loan funding
0 €Start date
15.08.2025Expected end date
30.06.2026Dimension
ResilienceComponent
National Health ServiceInvestment
Construction of the East Lisbon Hospital and equipment for hospitals in Lisbon and the Tagus ValleyOperation code
05/C01-i04/2025.P17782Summary
A requalificação das Unidades de Cuidados Intensivos (UCI) da Unidade Local de Saúde de Amadora/Sintra (ULSASI), nomeadamente das Unidades de Cuidados Intensivos Cardíacos (UCIC) e das Unidades de Cuidados Intensivos de Medicina Intensiva (UCI-I, UCI-II e UCI-III), é uma necessidade urgente para garantir que os cuidados prestados aos doentes críticos sejam seguros, eficazes e atualizados de acordo com os avanços da medicina moderna. As UCI da ULSASI desempenham um papel essencial no tratamento de doentes com patologias graves, especialmente em contextos de choque cardiogénico, insuficiência cardíaca aguda e síndromes coronárias agudas.A requalificação dos espaços físicos, a modernização dos equipamentos e a implementação de novos protocolos visam melhorar os resultados clínicos, otimizar o fluxo de trabalho e proporcionar melhores condições de trabalho para os profissionais de saúde. A evolução do quadro clínico dos doentes críticos exige que as UCI se adaptem às novas realidades clínicas, que envolvem intervenções cada vez mais complexas e uma maior necessidade de monitorização hemodinâmica avançada.Este projeto também visa responder a questões estruturais e tecnológicas, incluindo a atualização dos sistemas de ventilação, monitorização contínua e multiorgânica e a melhoria das condições de isolamento para doentes com patologias infeciosas. A intervenção será realizada com o objetivo de garantir a eficiência operacional das UCI, reduzir os tempos de internamento e minimizar os riscos de complicações nos doentes, melhorando assim a qualidade dos cuidados prestados.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
1,84 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 25 %,Where was the money spent
By county
1 county financed .
-
Amadora 1,84 million € ,