Project sheet

Name

Remodelação e beneficiação do serviço de Anatomia Patológica

Total project amount

1,69 million €

Amount paid

421,52 thousand €

Non-refundable funding

1,69 million €

Loan funding

0 €

Start date

01.09.2025

Expected end date

30.06.2026

Dimension

Resilience

Component

National Health Service

Investment

Construction of the East Lisbon Hospital and equipment for hospitals in Lisbon and the Tagus Valley

Operation code

05/C01-i04/2025.P17738

Summary

O presente projeto visa a remodelação e ampliação do Serviço de Anatomia Patológica do Instituto Português de Oncologia de Lisboa Francisco Gentil (IPOLFG), respondendo a limitações críticas de espaço, funcionalidade e obsolescência tecnológica. A intervenção irá permitir dotar o serviço com condições adequadas para garantir a qualidade, segurança e rastreabilidade dos processos laboratoriais associados ao diagnóstico oncológico.Com uma área de intervenção total de 1.515 m², o projeto abrange os pisos -1 e 0 do Pavilhão Central do IPOLFG, reorganizando funcionalmente o serviço para melhor articular os espaços laboratoriais, administrativos e de apoio. A proposta contempla a centralização das unidades funcionais, a eliminação de circuitos ineficientes e a criação de novas zonas técnicas e laboratoriais, com destaque para áreas de macroscopia, citopatologia, fluorescência e banco de tumores.A intervenção será realizada de forma faseada para garantir a manutenção da atividade clínica durante a execução da obra, com início previsto para junho de 2025 e conclusão em junho de 2026. O valor total do investimento é de 1.737.261,16€, sendo parcialmente financiado por fundos próprios, dada a ultrapassagem da dotação definida em Aviso.Com este projeto, o IPO Lisboa reforça a sua missão enquanto referência nacional em oncologia, garantindo a sustentabilidade e modernização do seu parque infraestrutural em alinhamento com os objetivos estratégicos do Plano de Recuperação e Resiliência

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

2,5
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

1,69 million €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 25 %,

Where was the money spent

By county

1 county financed .

  • Lisboa 1,69 million € ,
Source EMRP