Project sheet

Name

Eficiência Energética em Edifícios da Administração Pública Central

Total project amount

977,45 thousand €

Amount paid

195,49 thousand €

Non-refundable funding

977,45 thousand €

Loan funding

0 €

Start date

07.12.2021

Expected end date

31.12.2025

Dimension

Climate Transition

Component

Energy efficiency in buildings

Investment

Energy efficiency in central public administration buildings

Operation code

01/C13-i02/2021.P103

Summary

A intervenção que a entidade beneficiária se propõe executar, tem como principais objetivos, os seguintes: Tornar o edifício da Cantina mais eficiente energeticamente; Promover a extensão da vida útil do edifício, através da correção de patologias construtivas; Promover a melhoria do conforto dos seus utilizadores; Redução da fatura de energia e consequentemente a emissão de gases com efeito de estufa (GEE); Promover o aumento do desempenho hídrico do edifício; Apostar na utilização de energias renováveis Redução de recursos energéticos, hídricos e de materiais; Promover a eficiência dos sistemas técnicos. As intervenções que se pretendem efetuar resultam das medidas propostas na auditoria energética e incidem sobretudo na: - Envolvente opaca: Aplicação de isolamento tipo ETICS nas fachadas superiores do edifício; - Envolvente Envidraçada: substituição dos vãos horizontais envidraçados simples por envidraçados duplos; -Iluminação: Substituição de 667 luminárias com recurso a iluminação LED; - Sistemas Técnicos: Instalação de Caldeiras de condensação; Substituição de Chillers/Bomba de Calor; Substituição das bombas associadas ao AQS; substituição das UTA por outras mais eficientes; - Energias Renováveis: Instalação de um sistema solar fotovoltaico para produção de energia elétrica (autoconsumo) e Instalação de um Sistema Solar Térmico; - Eficiência hídrica: substituição de 69 torneiras da cozinha e dos balneários por soluções mais eficientes. Com a presente candidatura estima-se uma redução de 31,8% de consumo de energia primária (936.554,51 kWhEP/ano) e 33,02% na redução das emissões de CO2 (120,04 tCO2 eq/ano).

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

2,8
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

977,45 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 20 %,

Where was the money spent

By county

1 county financed .

  • Braga 977,45 thousand € ,
Source AD&C, EMRP
16.05.2024