PRR Project
comUN1DAde
Project sheet
Name
comUN1DAdeTotal project amount
50 thousand €Amount paid
35 thousand €Non-refundable funding
50 thousand €Loan funding
0 €Start date
12.10.2021Expected end date
31.12.2022Dimension
ResilienceComponent
Social InterventionInvestment
Integrated operations in deprived communities in the Metropolitan Areas of Lisbon and PortoOperation code
01/C03-i06.01/2021.P761Summary
Este Projeto nasce da vontade do Grupo Comunitário da Flamenga (GCF) em complementar a sua intervenção com meios para acionar respostas inovadoras e auto-sustentáveis às questões identificadas por residentes num Diagnóstico Participativo (DP). Face aos desafios socioeconómicos, ambientais,culturais e urbanísticos elencados, surgiram no DP propostas para ampliar a ação do GCF nestas áreas e gerar melhorias efetivas no Bem-Estar da Comunidade. É um Projeto co-gerido pelo GCF, de natureza participativa e integrada, que visa garantir a Sustentabilidade sistémica do território, numa lógica democrática bottom-up e com parcerias consolidadas, o que potenciará a sua continuação findo o Programa. As várias atividades interligam-se e complementam-se, contando com mediadores (at. 1,2,3) para fomentar as várias dinâmicas comunitárias, nas áreas de: formação, empregabilidade e empreendedorismo solidário,integração sociocultural, sustentabilidade ambiental, saúde comunitária e requalificação urbana.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
50 thousand €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 70 %,Where was the money spent
By county
1 county financed .
-
Lisboa 50 thousand € ,