Fase Complementar de Recuperação Ambiental das Antigas Áreas Mineiras de Covas e Jales

On this page

Project sheet

Project name

Fase Complementar de Recuperação Ambiental das Antigas Áreas Mineiras de Covas e Jales

Financing amount

4,7 million €

Executed amount

618,5 thousand €

Policy Objectives

+ Verde

Expected start date

16.08.2021

Expected end date

31.12.2027

Specific objective

Proteger e preservar a natureza, a biodiversidade e os espaços verdes, inclusive nas zonas urbanas.

Modality

Subvenção

Operation code

NORTE2030-FEDER-02023400

Summary

Evitar a contaminação de massas de água de boa qualidade; recolher e tratar adequadamente os efluentes e reabilitar as vertentes hidrológica e ambiental na envolvente mineira; evitar a contaminação de solos; elevar a capacidade de uso dos solos; confinar os depósitos de minério pobre e de outros resíduos; contribuir para o saneamento ambiental; garantir uma re-vegetação integrada no meio envolvente; minimizar os riscos e adotar medidas de prevenção, designadamente vedar e sinalizar as áreas mineiras; contribuir para a valorização ecológica e da biodiversidade da área de influência e contribuir para a sustentabilidade local.

Beneficiaries

Main beneficiary

Applications

The Calls for Applications provide an opportunity for public and private entities to obtain financing for projects that boost the Portuguese economy. Each notice defines a specific value for investment, made available to beneficiaries through bidding or invitation.

Projects submitted to the competition are evaluated by specific entities, based on selection criteria established in the registration notices. When applicable, evaluation grades are assigned to projects.

Final grade on the application

Notapplicable

Operation code

NORTE2030-2024-9

Name of the notice

Recuperação Ambiental de áreas mineiras abandonadas

Geographic distribution

Financiamento total do projeto

4,7 million €

Percentage of value already executed for the implementation of projects

13 %,
Where the money was invested

By countys

2 counties financed .

  • Vila Nova de Cerveira 2,36 million € ,
  • Vila Pouca de Aguiar 2,36 million € ,