Name

FELGUEIRA+ACESSIVEL 1

Total project amount

14,46 thousand €

Amount paid

4,34 thousand €

Non-refundable funding

14,46 thousand €

Loan funding

0 €

Start date

01.03.2024

Expected end date

01.03.2025

Dimension

Resilience

Component

Social Intervention

Investment

360° Accessibility

Operation code

05/C03-i02/2023.P5767

Summary

Para o presente projeto, pressupõe-se a apresentação do seguinte mapa de trabalhos com as seguintes intervenções: - Abertura de vão na parede que liga o quarto do utente à instalação sanitária (IS) para que a grua móvel que transporta o utente tenha uma passagem direta entre o quarto e a instalação sanitária;- Instalação de porta deslizante (de correr) na parede pelo lado do quarto do utente;- Remoção da banheira existente na instalação sanitária;- Substituição do pavimento atual da IS para inserção de “Walking Shower”, de modo a ter um pavimento drenante continuo, sem ressaltos, bem como a instalação de misturadora de duche com coluna e suporte de chuveiro de mão, e respetivo ralo de pavimento;- Fornecimento e montagem de calha com cortina tipo hospitalar em “L” com respetivos assessórios, suportes e ligações. - Remoção da base de duche existente na instalação sanitária;- Eliminação do bidé;- Substituição e recolocação da sanita com de modo a disponibilizar mais espaço para mobilidade da cadeira de rodas e da grua, e inserção de novo tubo de descarga, bem como torneiras e demais acessórios.- Substituição do atual lavatório por outro de maior altura de forma que o cuidador possa inserir a cadeira do utente na parte de baixo do lavatório, facilitando a realização da higiene, e inserção de novo tubo de descarga, bem como torneiras e demais acessórios;- Substituição dos azulejos nas zonas inferiores das paredes onde ocorreram trabalhos de demolição e de substituição do equipamento sanitário;- Colocação de proteções em aço escovado nas portas de IS, Quarto, cozinha e sala de estar.Os trabalhos propostos acima são os considerados necessárias para eliminar as barreiras arquitetónicas existentes na habitação. Neste sentido, o presente projeto irá contribuir diretamente para o aumento das condições de acessibilidade em habitação do destinatário final permitindo uma melhor mobilidade.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

80,0
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

14,46 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 30 %,

Where was the money spent

By county

1 county financed .

  • Felgueiras 14,46 thousand € ,
Source EMRP