PRR Project
Implementação de uma central de cogeração a biomassa florestal
Project sheet
Name
Implementação de uma central de cogeração a biomassa florestalTotal project amount
12,34 million €Amount paid
6,01 million €Non-refundable funding
12,34 million €Loan funding
0 €Start date
15.09.2023Expected end date
14.09.2025Dimension
Climate TransitionComponent
Decarbonising IndustryInvestment
Decarbonising IndustryOperation code
03/C11-i01/2022.P4954Summary
A JAF-Madeiras desenvolverá um projeto de investimento que lhe permita descarbonizar a sua prática, com ganhos ao nível da resiliência e competitividade, como também pela redução da sua pegada de carbono, contribuindo para o desafio da transição carbónica da indústria em linha com as políticas europeias e nacionais em termos de clima e ambiente.Para tal, irá instalar uma central de cogeração a biomassa florestal e equipamentos acessórios, para tornar a instalação de briquetes/pellets significativamente mais eficientes do ponto de vista energético, redefinindo para isso o seu processo industrial associado à geração de calor, com o benefício adicional de gerar também eletricidade verde para autoconsumo.Alcançando assim, no ano de conclusão do projeto uma produção, em média, 2,066 MW de eletricidade a partir de fontes renováveis em regime de autoconsumo (cogeração através de biomassa, privilegiando a circularidade) e, bem assim, uma redução de 2.575,36 tonCO2-eq e de 3.037,97 tep.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
12,34 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 48,7 %,Where was the money spent
By county
1 county financed .
-
Oleiros 12,34 million € ,