Instalação de central fotovoltaica na Fábrica da FilkempTotal project amount
598,21 thousand €Amount paid
452,42 thousand €Non-refundable funding
598,21 thousand €Loan funding
0 €Start date
17.01.2023Expected end date
30.04.2024Dimension
Climate TransitionComponent
Decarbonising IndustryInvestment
Decarbonising IndustryOperation code
03/C11-i01/2022.P3159Summary
A Filkemp - Indústria De Filamentos, S.A., fundada em 1998, é uma referência global na produção de monofilamentos poliméricos que servem de base à produção de filamentos técnicos para a indústria de papel, bandas transportadoras, filamentos para impressão 3D, entre outras. Recentemente, a Filkemp tem vindo a apostar na diminuição da sua pegada carbónica, através da redução dos desperdícios, bem como do aumento da sua eficiência energética, pretendendo agora, dar continuidade aos seus esforços, nos domínios energético e ambiental.Com o presente projeto, a Filkemp pretende instalar um parque solar, que permitirá suprir uma quantidade significativa das suas necessidades de energia elétrica, reduzindo, simultaneamente, a sua dependência de eletricidade de origem não renovável. Este investimento, que totalizará cerca de 1 M?, entre 2023 e 2024, permitirá à Empresa reduzir as suas emissões de gases de efeito de estufa (GEE) em aproximadamente 17,8%.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
598,21 thousand €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 75,6 %,Where was the money spent
By county
1 county financed .
-