Name
Redução de Perdas de Água no Sector Urbano - Investimentos com vista à redução de perdas reais nos sistemas de disTotal project amount
523,5 thousand €Amount paid
0 €Non-refundable funding
523,5 thousand €Loan funding
0 €Start date
01.01.2021Expected end date
31.03.2026Dimension
ResilienceComponent
Water managementInvestment
Algarve Regional Water Efficiency PlanOperation code
03/C09-i01.01/2023.P4709Summary
O projeto "Redução de Perdas de Água no Sector Urbano", promovida pela Inframoura, incide em investimentos com vista à redução de perdas reais nos sistemas de distribuição de água, designadamente a renovação ou substituição de componentes problemáticos por apresentarem elevados níveis de perdas reais de água e cuja intervenção permita obter ganhos significativos de eficiência hídrica em zonas de rede com pior desempenho em perdas reais. Neste contexto, o presente projeto irá focar-se na reabilitação de um setor do subsistema de abastecimento de água de Vilamoura (Setor D.S3-H2), que é constituído por uma estação hidropressora, H2, aduzida através de uma conduta gravítica, com cerca de 890 metros de extensão, com origem no reservatório R6 e uma Zona de Monitorização e Controlo (ZMC), ZMC Hidropressora H2, com 3,6 km de condutas de distribuição.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
523,5 thousand €
Total amount of the project
Where was the money spent
By county
1 county financed .
-
Loulé 523,5 thousand € ,