PRR Project
MEcoPAV02 - Misturas Betuminosas Ecológicas para Pavimentação de Estradas
Project sheet
Name
MEcoPAV02 - Misturas Betuminosas Ecológicas para Pavimentação de EstradasTotal project amount
1,23 million €Amount paid
283,88 thousand €Non-refundable funding
1,23 million €Loan funding
0 €Start date
01.01.2023Expected end date
31.12.2024Dimension
Climate TransitionComponent
Decarbonising IndustryInvestment
Decarbonising IndustryOperation code
02/C11-i01/2022.PC658999822-00471879Summary
O projeto irá concorrer para a maximização da economia circular e, consequente, diminuição da pegada de carbono no fabrico de misturas betuminosas para a pavimentação de estradas, na central de misturas betuminosas da Mota-Engil Engenharia e Construção, S.A., situada na cidade de Famalicão. Para o efeito, os desígnios deste projeto são: 1) readaptação de equipamentos existentes para maximizar a incorporação de misturas betuminosas fresadas, em detrimento da utilização de matérias-primas naturais (?virgens?), aumentando significativamente a circularidade; 2) diminuir a dependência da utilização de combustíveis fósseis, através da substituição dos equipamentos existentes no processo de fabrico que utilizem este tipo de combustível como fonte de energia; e 3) apostar na transformação digital, incorporando soluções digitais de apoio à decisão, aumentando a eficiência de utilização de recursos.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
1,23 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 23 %,Where was the money spent
By county
1 county financed .
-
Amarante 1,23 million € ,