Name
PAEC MCM 2025, PLANO DE AÇÃO ENERGÉTICA E CLIMÁTICA DA MARTIFER CONSTRUÇÕES METALOMECÂNICASTotal project amount
1,49 million €Amount paid
929,75 thousand €Non-refundable funding
1,49 million €Loan funding
0 €Start date
01.09.2022Expected end date
31.03.2024Dimension
Climate TransitionComponent
Decarbonising IndustryInvestment
Decarbonising IndustryOperation code
02/C11-i01/2022.PC658421348-00471762Summary
Através do presente projeto, a MARTIFER Construções Metalomecânicas vai concretizar o seu Plano de Ação Energética e Climática 2025 - PAEC MCM 2025, cujas principais Medidas passam por apostar na Transição Energética para Energias Renováveis (eólica); diminuir o recurso a combustíveis fósseis; aumentar a racionalidade e eficiência energética das suas operações, bem como apostar em princípios e funcionalidades da I4.0 quer para gerir e monitorizar os consumos energéticos, quer para desmaterializar processos.Com a concretização do PA EC MCM 2025 a empresa diminuirá em mais de 50% quer os consumos de energia (tep), quer as emissões de GEE (diretas e indiretas), contribuindo assim para a sustentabilidade das suas práticas, bem como para o PNEC2030 e RNC2050.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
1,49 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 62,3 %,Where was the money spent
By county
1 county financed .
-
Oliveira de Frades 1,49 million € ,