Jump to main page content
Loading...

Project sheet

Name

Medição e Controlo das Perdas de Água no Concelho de Albufeira

Total project amount

775,69 thousand €

Amount paid

607,42 thousand €

Non-refundable funding

775,69 thousand €

Loan funding

0 €

Start date

01.01.2021

Expected end date

31.03.2026

Dimension

Resilience

Component

Water management

Investment

Algarve Regional Water Efficiency Plan

Operation code

02/C09-i01.01/2023.P3792

Summary

A presente operação visa a implementação de zonas de medição e de controlo ativo de perdas de água nas redes de distribuição do concelho de Albufeira, nomeadamente através de: - Aquisição de serviço para o “Plano de eficiência hídrica – reforço da pesquisa ativa de fugas com recurso a Geofone”, que terá como objetivo reduzir as perdas de água não visíveis na rede de abastecimento de água; - Prestação de serviços de “Interface para exportar dados do Gestwater para Postgres”, como objetivo de para possibilitar a análise e constituição de histórico, para uma melhor gestão das perdas reais de água; - Instalação de um sistema Wi-Fi entre o Furo e o Reservatório do Malhão, com o objetivo de instalação de um sistema de comunicação de dados de funcionamento das bombas e o existente no reservatório que são integrados no sistema de telegestão. - Fornecimento de contadores e caudalímetros de água e sistemas de telemetria, para posterior análise de dados para a redefinição de Zonas de Medição e Controlo (ZMC) existentes e constituição de novas ZMC; - Remodelação do sistema de telegestão, com o objetivo de criar novas zonas de medição e controlo da rede de abastecimento de água, bem como a construção e remodelação de acessórios para contribuição de redução de perdas de água. - Aquisição de software para monitorização e controlo de perdas de água, com o objetivo de obter uma gestão integrada das ZMC, bem como a mitigação de perdas com integração operacional. Trata-se de um investimento no montante de 1 098 340,19€, fulcral para a redução das perdas de água no concelho.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

2,6
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

775,69 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 78,3 %,

Where was the money spent

By county

1 county financed .

  • Albufeira 775,69 thousand € ,
Source AD&C, EMRP
18.09.2024