Name
From Fossil to ForestTotal project amount
34,45 million €Amount paid
9,45 million €Non-refundable funding
34,45 million €Loan funding
0 €Start date
01.07.2021Expected end date
30.06.2026Dimension
ResilienceComponent
Investment and innovationInvestment
Green Agendas/Alliances for Business InnovationOperation code
02/C05-i01.02/2022.PC644920945-00000036Summary
O presente «Pacto de Inovação» visa o desenvolvimento de embalagens e produtos à base de celulose para a substituição de plásticos fósseis. Neste contexto, o mesmo compreende os seis work packages seguintes: (1) pastas de alto rendimento e papéis castanhos; (2) papéis com maior resistência mecânica; (3) papéis com propriedades barreira; (4) biocompósitos; (5) sensores em papel para embalagem inteligente e (6) celulose moldada para embalagem rígida. A atuação do Pacto de Inovação divide-se num conjunto de objetivos específicos, que serão endereçados por um consórcio, constituído por 27 promotores cujas competências técnicas e tecnológicas, se complementam. Liderado pela Navigator Paper Setúbal, S.A., (NPS) este consórcio congrega a capacidade financeira e os recursos técnicos necessários à realização deste pacto, envolvendo um investimento de 118,6 M€, em distintos projetos empresariais de reindustrialização, assentes numa base de I&D e inovação.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
34,45 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 27,4 %,Where was the money spent
By county
17 counties financed .
-
Aveiro 12,34 million € ,
-
Setúbal 8,23 million € ,
-
Lisboa 3,62 million € ,
-
Almada 1,81 million € ,
-
Covilhã 1,51 million € ,