PRR Project
H2Enable - The Hydrogen Way for Our Chemical Future
Project sheet
Name
H2Enable - The Hydrogen Way for Our Chemical FutureTotal project amount
60,27 million €Amount paid
13,86 million €Non-refundable funding
60,27 million €Loan funding
0 €Start date
01.07.2021Expected end date
30.06.2026Dimension
ResilienceComponent
Investment and innovationInvestment
Green Agendas/Alliances for Business InnovationOperation code
02/C05-i01.02/2022.PC644865888-00000009Summary
A Agenda H2Enable tem como objetivo acelerar e transformar a cadeia de valor do hidrogénio verde em Portugal, a partir do Complexo Químico de Estarreja, onde estão localizados dois dos maiores players portugueses da indústria química ? Bondalti e Air Liquide.Os promotores empresariais, juntamente com o apoio de duas entidades do Sistema de Investigação e Inovação ? a Faculdade de Engenharia da Universidade do Porto e o Laboratório Colaborativo HyLab ? e da entidade gestora do Cluster químico e petroquímico em Portugal ? APQuímica ? realizarão os necessários esforços de Investigação & Desenvolvimento, Investimento Produtivo e Promoção e Disseminação para levar a cabo a construção de uma fábrica de hidrogénio verde de grande escala fundamental para o país, bem como das respetivas infraestruturas de suporte, que permitirão que o hidrogénio verde aí produzido chegue a um número elevado de utilizadores e consumidores, em vários setores económicos.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
60,27 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 23 %,Where was the money spent
By county
4 counties financed .
-
Estarreja 57,03 million € ,
-
Sines 1,94 million € ,
-
Porto 1,16 million € ,
-
Lisboa 140,88 thousand € ,