PRR Project
Eficiência energética em edifícios públicos da Madeira
Project sheet
Name
Eficiência energética em edifícios públicos da MadeiraTotal project amount
14 million €Amount paid
0 €Non-refundable funding
14 million €Loan funding
0 €Start date
03.07.2024Expected end date
31.12.2025Dimension
Climate TransitionComponent
REPowerEUInvestment
Energy efficiency in public buildings in MadeiraOperation code
01/C21-i04-RAM/2024.PC21-i04-RAM-p1Summary
Intervenções de reabilitação energética que implicam a implementação de soluções integradas e que abrangem edifícios de titularidade pública afetos aos setores da educação, saúde, desporto, administração regional, investigação, emprego, entre outros
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
14 million €
Total amount of the project
Where was the money spent
By county
1 county financed .
-
Funchal 14 million € ,