Project sheet

Name

Incubadora de Conhecimento Informático

Total project amount

636,47 thousand €

Amount paid

190,94 thousand €

Non-refundable funding

636,47 thousand €

Loan funding

0 €

Start date

01.01.2022

Expected end date

31.12.2025

Dimension

Resilience

Component

Qualifications and Skills

Investment

Modernising education and vocational training services and establishments

Operation code

01/C06-i01.01/2022.P1558

Summary

Reabilitação das instalações: substituição de portas de acesso aos espaços-sala para garantir a segurança dos equipamentos e recursos que ai venham a ser instalados. Modernização das infraestruturas tecnológicas: rede elétrica com uma distribuição de tomadas adequadas à reconfiguração do espaço-sala e que comporte a ligação/alimentação dos equipamentos informáticos e de apoio às atividades de aprendizagem existentes; rede informática por cabo (CAT7 ou 8) que comporte a ligação/alimentação dos equipamentos informáticos e de apoio às atividades de aprendizagem existentes; rede informática sem fios com pontos de acesso preparados para aceitar e gerir 60 ligações de dispositivos em simultâneo por sala. Reequipamento mobiliário: cadeiras com suporte de trabalho individual; mesas para trabalho de grupo reconfiguráveis; mesas de trabalho e bancadas técnicas para preparação e operacionalização de atividades experimentais (áudio, vídeo, robots programáveis, ...); mini estúdio multimédia para gravação de vídeo e áudio. Aquisição de recursos tecnológicos: tablets e computadores portáteis para trabalhos individuais e de grupo; computadores fixos (torres) para tratamento de imagem/vídeo/áudio e programação final dos robots; conjunto de luz e câmara de de gravação de vídeo/áudio; impressora 3D para impressão de objetos 3D desenvolvidos para projetos.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

72,0
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

636,47 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 30 %,

Where was the money spent

By county

1 county financed .

  • Espinho 636,47 thousand € ,
Source AD&C, EMRP
16.05.2024