Information portal on various topics of management of public resources of the Portuguese State

Project sheet

Name

Pentaline + Green - Aumento da produção da energia de fonte renovável e seu armazenamento

Total project amount

139,4 thousand €

Amount paid

106,21 thousand €

Non-refundable funding

139,4 thousand €

Loan funding

0 €

Start date

01.01.2023

Expected end date

31.12.2024

Dimension

Climate Transition

Component

Decarbonising Industry

Investment

Decarbonising Industry

Operation code

03/C11-i01/2022.P2090

Summary

O projeto Pentaline + Green consiste na implementação de medidas que permitam reduzir o consumo energético proveniente de fontes não renováveis.Para assegurar a estratégia de descarbonização a Pentaline pretende com este projeto instalar dois sistemas de produção de energia a partir de fontes renováveis, energia solar e energia eólica. Os sistemas a instalar, um sistema solar fotovoltaico e um sistema eólico, são ambos para consumo próprio. Atualmente a Pentaline já possui um sistema de produção de energia solar. Contudo, o sistema instalado permite apenas responder a uma pequena parte das suas necessidades e não têm possibilidade de armazenar a energia não consumida. Assim, adicionalmente aos sistemas de energia renováveis, neste projeto, prevê-se também a aquisição de um sistema de armazenamento da energia produzida. Deste modo será minimizada a necessidade de recurso à rede de energia elétrica nacional e também assegurado que não haverá desperdícios da energia produzida.

Beneficiaries

Within the scope of the Recovery and Resilience Plan, two types of beneficiaries are responsible for carrying out the projects and using the funding provided. Due to their similar role, the reference to these two types of beneficiaries has been simplified and unified under the term "Beneficiary".
The two types are::
  • Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
  • Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.

Call for applications

As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.

The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.

Final evaluation score

4,6
Important note

The components for calculating the assessment score can be found in the selection criteria document mentioned below.

Selection criteria

The funding selection criteria to which this project and its final beneficiary were subject and its score can be found in detail on the Recuperar Portugal platform.

Beneficiaries

Intermediate beneficiaries

Beneficiaries

Procurement

Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.

To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.

Geographic distribution

139,4 thousand €

Total amount of the project

Percentage of the amount already paid for implementing projects

, 76,2 %,

Where was the money spent

By county

1 county financed .

  • Vale de Cambra 139,4 thousand € ,
Source EMRP
24.11.2026
All themes
Transparency without leading