PRR Project
Projeto de Descarbonização e melhoria da Eficiência Energética das instalações industriais da D.I.N., SA.
Project sheet
Name
Projeto de Descarbonização e melhoria da Eficiência Energética das instalações industriais da D.I.N., SA.Total project amount
182,51 thousand €Amount paid
182,51 thousand €Non-refundable funding
182,51 thousand €Loan funding
0 €Start date
01.02.2023Expected end date
31.01.2025Dimension
Climate TransitionComponent
Decarbonising IndustryInvestment
Decarbonising IndustryOperation code
03/C11-i01/2022.P2087Summary
A D.I.N. - Desenvolvimento e Inovação Nutricional S.A. é especializada na Formulação, Desenvolvimento e Fabrico de Pré-misturas para nutrição e saúde animal. As suas instalações produtivas (em Santa Comba Dão) dividem-se em Fábrica de Alimentos Completos, Fábrica de Pré-Misturas e Laboratório, e a sua atividade industrial assenta essencialmente em consumos de eletricidade, gás natural e GPL. O diagnóstico da situação de 2021 revelou consumos energéticos e emissões de GEE na ordem dos 127 tep/ano e 113 tCO2/ano, respetivamente, associados a componentes energéticas e de processo específicos.Este projeto tem como objetivo reforçar a competitividade e sustentabilidade da DIN, SA. e assenta em 5 medidas visando a implementação de Tecnologias Baixo Carbono, melhoria da Eficiência Energética e incoporação de Energia de fonte renovável (solar), Como resultado, espera-se em 2025 uma redução de 34,7% e de 32,1% de emissões de GEE e de consumos energéticos, respetivamente
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
182,51 thousand €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 100 %,Where was the money spent
By county
1 county financed .
-
Santa Comba Dão 182,51 thousand € ,