PRR Project
Aumento da eficiência energética na produção de latão e redução da respectiva pegada de carbono (effi-BRASS)
Project sheet
Name
Aumento da eficiência energética na produção de latão e redução da respectiva pegada de carbono (effi-BRASS)Total project amount
1,54 million €Amount paid
1,12 million €Non-refundable funding
1,54 million €Loan funding
0 €Start date
01.10.2022Expected end date
30.09.2024Dimension
Climate TransitionComponent
Decarbonising IndustryInvestment
Decarbonising IndustryOperation code
02/C11-i01/2022.PC654599756-00470941Summary
Com effi-BRASS, a ASBW pretende adaptar as suas linhas de produção a ligas de latão, com efeitos benéficos significativos sobre a respetiva pegada de carbono, eficiência energética e a economia circular. O latão é um material 100% reciclável, e a matéria-prima da empresa é maioritariamente sucata, incluindo o aproveitamento dos resíduos/subprodutos resultantes do seu próprio processo produtivo e dos seus clientes. Pretende-se potenciar estas características, tornando mais limpas e eficientes as operações da ASBW. Com a capacidade providenciada pelo plano proposto, a ASBW intensificará a oferta de alternativas a metais mais poluentes e mais eficientes do ponto de vista energético. Além da modernização da produção para permitir a digitalização, monitorização e controlo de defeitos de forma a optimizar a eficiência energética, é prevista a expansão do parque de painéis fotovoltaicos para autoconsumo e a instalação de sistemas para o tratamento de efluentes de água e recuperação do calor.
Beneficiaries
The two types are::
- Direct Beneficiaries are those whose funding and projects to implement are part of the Recovery and Resilience Plan that has been negotiated and approved by the European Union;
- Final Beneficiaries are those whose funding and projects to implement are approved following a selection process through Calls for Applications.
Call for applications
As part of the Call for Applications, submissions are requested to select the projects and final beneficiaries to whom funding will be awarded. Specific selection criteria are defined for each call, which must be reflected in the applications submitted and assessed.
The project is appraised on the basis of its compliance with the selection criteria laid down in the calls for applications, and a final score may be awarded, where applicable.
Final evaluation score
The components for calculating the assessment score can be found in the selection criteria document mentioned below.
Selection criteria
Beneficiaries
Intermediate beneficiaries
Procurement
Beneficiaries representing public entities implement their project by signing one or more contracts with suppliers for goods or services through public procurement procedures.
To ensure and provide the utmost transparency in all these contracts, a list of the contracts that were signed under this project is available here, along with the information available on the Base.Gov platform. Please note that, according to the legislation in force at the time the contract was signed, some exceptions do not require the publication of the contracts signed on this platform, and, therefore, no information is available in such cases.
Geographic distribution
1,54 million €
Total amount of the project
Percentage of the amount already paid for implementing projects
, 72,7 %,Where was the money spent
By county
1 county financed .
-
Santa Maria da Feira 1,54 million € ,